The plan of complex of scheduled maintenance and repair works by PJSC "Ukrtransgaz" in 2016 with the reduction of gas transportation
Period Duration (hours) Сomplex of scheduled maintenance Max capacity
17/05-20/05 96(120) Scheduled maintenance on gas pipelines SHPK-SHDK-EDK and KZU-1,2 on CS Berdychiv (120 hours) and CS Rogatyn. Repair of pipeline. Entry IP Sudzha (P=55) 
Q=24 mcm/day 
24/05-27/05 96(250) Scheduled maintenance on CS of gas pipelines UPU and «Progress» : CS Grebenka (UPU, 250 hours), CS Stavyshche, CS Bar, CS Bogorodchany. Repair of pipeline.

Exit IP Beregovo, IP Tekovo, IP Uzhgorod Q=255 mcm/day

Entry IP Sudzha (P=75)
Q=210 mcm/day

31/05-03/06 96 Scheduled maintenance on gas pipeline SHPK-SHDK-EDK on CS Yagotyn. 
Repair of pipeline.
Entry IP Sudzha (P=55) 
Q=24 mcm/day 
07/06-10/06 96

Scheduled maintenance on gas pipelines KK and KZU-1,2 on CS Grebenka, CS Krasilov.
Repair of pipeline.

Entry IP Sudzha (P=55) 
Q=24 mcm/day
21/06-24/06 96

Scheduled maintenance on gas pipelines SHPK-SHDK-EDK, KK and KZU-1,2 on CS Glushkov and CS Ternopil.
Repair of pipeline.

Entry IP Sudzha (P=55) 
Q=24 mcm/day
05/07-08/07 96

Scheduled maintenance on gas pipelines EKKP, KACHB, ATI on CS Zenkovska, CS Zadneprovska, CS YU.Bugska, CS Tarutyno, CS Orlovka-1.
Repair of pipeline.

Exit IP Orlovka Q=45 mcm/day
 
19/07-22/07 96 Scheduled maintenance on gas pipeline «Soyuz»: CS Novopskov, CS Borovaya, CS Pervomayska, CS Mashevka, CS Kremenchyk, CS Gaysin, CS Gusatyn, CS Hust. 
Repair of pipeline. Replacement of 0,5 km of pipe (on gas pipeline «Soyuz» 1230-1263,96 km)
Exit IP Beregovo, Tekovo, Uzhgorod Q=226 mcm/day
Entry IP Sudzha(P=75) Q=230 mcm/day
Stop of gas transportation on pipeline «Soyuz» on section from CS Novopskov to CS Mashevka 
26/07-29/07 96 Scheduled maintenance on gas pipeline «Soyuz» CS Alexandrovka, CS Talnoe, CS Bar, CS Bogorodchany.
Repair of pipeline.

 

Exit IP Beregovo, IP Tekovo, IP Uzhgorod Q=226 mcm/day

Entry IP Sudzha (P=75)
Q=230 mcm/day

July-August 96 Scheduled maintenance on gas pipeline DUG-2 on CS Dolyna, CS Rososh and CS Uzhgorod. Repair of pipeline. Exit IP Beregovo, IP Tekovo, IP Uzhgorod Q=230 mcm/day
09/08-12/08 96 Scheduled maintenance on gas pipeline SHPK-SHDK-EDK on CS Lubny. Repair of pipeline. Entry IP Sudzha (P=55)
Q=24 mcm/day
16/08-19/08 96 Scheduled maintenance on gas pipelines EKK, ATI on CS Romny, CS Reshetilovka, CS Kirovogradska, CS Ananev, CS Orlovka-2. Repair of pipeline and IP Grebennyky Exit IP Orlovka Q=45 mcm/day
30/08-02/09 96 Scheduled maintenance on gas pipelines EKK and EKD on CS Summyand on gas pipeline Komarno-Drozdovychy on CS Komarno. Repair of pipeline. Entry IP Sudzha (P=55)
Q=24 mcm/day
06/09-09/09 96 Scheduled maintenance on gas pipelines KK, KZU-1,2 on CS Romny and CS Boyarka. Repair of pipeline. Entry IP Sudzha (P=55)
Q=24 mcm/day
13/09-16/09 96

Fire works - installation of technological connections  between CS Zadneprovska and CS Kremenchug. Disconnection of area of gas pipeline KAB -6,5-6,9 km 

Exit IP Orlovka Q=18 mcm/day
20/09-24/09

96(240)

 

120

Scheduled maintenance on gas pipelines UPU and «Progress»: CS Romny (UPU, 240 hours), CS Sofievka, CS Ilintzi, CS Gusyatyn, CS Golyatyn.

Replacement of defect valves dn 1200 at pipeline crossing of the Dnipro on gas pipeline UPU — 3617,5 -3689,5 km and Progress — 3762,53-3788,8 km. Repair of pipeline.

Exit IP Beregovo, IP Tekovo, IP Uzhgorod Q=140 mcm/day

Entry IP Sudzha (P=75)
Q=85 mcm/day

24/09-30/09 144 Replacement of defect valves dn 1200 at pipeline crossing of the Dnipro on gas pipeline UPU — 3617,5 -3689,5 km and Progress — 3762,53-3788,8 km. Repair of pipeline.

Exit IP Beregovo, IP Tekovo, IP Uzhgorod Q=220 mcm/day

Entry IP Sudzha (P=75)
Q=190 mcm/day

04/10-07/10 96 Scheduled maintenance on gas pipeline SHPK-SHDK-EDK on CS Dykanka. Repair of pipeline. Entry IP Sudzha (P=55)
Q=24 mcm/day
October 96

Fire works - installation of technological connections between CS Zadneprovska and CS Kremenchug. Disconnection of area of gas pipeline Soyuz — 1724-1754 km.

Exit IP Beregovo, IP Tekovo, IP Uzhgorod Q=220 mcm/day

Entry IP Sudzha (P=75)
Q=230 mcm/day

 

 

Unscheduled maintenance and repair works by PJSC "Ukrtransgaz" in 2016 with the reduction of gas transportation
Period Duration  Сomplex of unscheduled maintenance Max capacity
- - - -